Tachyon 🌐 Global

Running a better workshop

Find the constraint, or improve nothing

An hour saved anywhere except the bottleneck is an illusion. Goldratt’s five focusing steps, on a workshop floor.

Bay 1 Bay 2 — slowest Bay 3 20 min 55 min 20 min Work arrives faster than Bay 2 clears it. Speeding up Bay 1 or 3 changes nothing.

Eliyahu Goldratt put it starkly in The Goal: an hour lost at the bottleneck is an hour lost for the whole system, and an hour saved anywhere else is a mirage. Workshops break this rule constantly — new scan tool, faster invoicing, a tidier parts room — and wonder why the number of cars out the door never moves.

What the constraint usually is

In an independent shop it is almost always one of four things, and rarely the one being optimised:

  • A hoist. Four bays, three hoists, and one of them is the only one that takes a van.
  • One technician. The person who gets every diagnostic job because nobody else can. Their queue is the shop's queue.
  • The counter. One advisor booking, quoting, phoning, invoicing. Work stops to wait on a conversation.
  • Parts arrival. Not a resource but a dependency, and the most common constraint of all.

The five steps, applied

Identify. Look for the queue. Work piles up in front of a constraint. If three cars are waiting on the diagnostic tech and the other bays have gaps, you have your answer without measuring anything.

Exploit. Make sure the constraint is never idle for a reason you control. If the diagnostic technician is the constraint, they should not be writing quotes, moving cars, or chasing parts. Protect their hours the way you would protect a machine you had just paid for.

Subordinate. Everything else runs at the constraint's pace. Booking more work than the bottleneck can absorb does not increase output; it increases the pile. This is the step shops skip, because taking a booking feels like winning.

Elevate. Only now spend money. Hire the second diagnostic tech, buy the fourth hoist, bring parts forward a day. Note that three free steps came first.

Repeat. Fix one constraint and it moves somewhere else. That is success, not failure — but it means last quarter's answer is not this quarter's.

Why shops get this wrong

Because every part of the shop can point at a local inefficiency, and fixing local inefficiency feels productive. The parts room genuinely is untidy. The invoicing genuinely is slow. Neither is why you did eleven cars last Tuesday instead of fourteen.

The discipline is to measure where work waits, not where people are busy. Those are different questions, and only the first one tells you what to fix.

1 Identify the constraint 2 Exploit it — never let it idle 3 Subordinate everything to its pace 4 Elevate it — only now spend money 5 · repeat

What this takes to measure

CapabilityFromWhy
Job boardStarterWhere work is queued, and in front of what.
Bays and schedulingStarterWhether the constraint is a bay or a person.
Time logsStarterHours at the constraint, separated from hours everywhere else.
Management exceptionsBusinessJobs that stalled, surfaced without someone going to look.

Further reading

  • Eliyahu Goldratt — The Goal (1984) — the five focusing steps.
  • Eliyahu Goldratt — Theory of Constraints (1990).