There is a result from queuing theory, named after John Little, that every workshop proves weekly without knowing it:
Lead time = work in progress ÷ throughput
If you have twenty cars open and you finish eight a day, the average car takes two and a half days — regardless of how fast anyone works. To get cars out faster you either finish more per day, or you have fewer open at once. Nothing else is available.
Why shops drift to high WIP
Because every individual decision to take the car in is correct. The customer is standing there. The bay looks free. Saying no feels like turning away money.
But a car accepted before there is capacity to work on it does not start earlier — it waits in a longer queue, pushing every other car back with it. The shop becomes busier and slower simultaneously, which is exactly how it feels on the floor.
The counterintuitive fix
Cap the number of jobs that may be open at once. A kanban board with a limit on the in-progress column is the whole mechanism: when the column is full, nothing new starts until something finishes.
Shops that try this report the same sequence. Week one feels wrong — bays appear idle while cars wait. Week three, turnaround has dropped sharply, nobody is chasing status, and the same number of cars go out, finished sooner.
What to measure
Count open jobs at 5pm each day for two weeks, and count jobs completed each day. Divide. That is your real lead time, and it is usually longer than the number you quote customers.
What this takes to measure
| Capability | From | Why |
|---|---|---|
| Job board with a work-in-progress view | Starter | How many jobs are genuinely open right now. |
| Appointments and scheduling | Starter | Booking to capacity instead of to the calendar. |
| Workshop reports | Professional | Completed per day, to put a number on throughput. |
Further reading
- John D. C. Little — “A Proof for the Queuing Formula L = λW” (1961).
- Donald Reinertsen — The Principles of Product Development Flow (2009) — on queues and WIP.